TUNNELING
1. The tunnels, the artificial underground passages are
constructed for
A. highways
B. railways
C. sewerage
D. All the above.
Answer => D
2. The following
tunnels were constructed in different countries for different purposes : 1.
Emperor Claudius built the first Roman tunnel 2. The first highway tunnel was
constructed in Hungary 3. The first underground railway tunnel was constructed
in Great Britain 4. The first navigational tunnel was constructed in France.
The correct chronological development of these tunnels is:
A. 4,1,3,2
B. 1,4,2,3
C. 2,3,1,4
D. 3,2,4,1.
Answer => B
3. For highways, tunnelling is preferred to if the open cut
exceeds :
A. 10 metres depth
B. 15 metres depth
C. 20 metres depth
D. 25 metres depth.
Answer => B
4. In case of railways,
A. a detour round the hill is preferred
B. a open cut is preferred
C. tunnelling is preferred
D. All the above.
Answer => C
5. A tunnel is found
more advantageous as compared to the alternate routes because it :
A. remains free from snow
B. reduces the cost by reducing the route distance
C. reduces the maintenance cost
D. All the above.
Answer => D
6. For initial
surveys of tunnels, the following activities are involved : 1. Marking portal
point with concrete pillars on the ground 2 Marking tunnel obligatory points on
the topographical maps 3. Preliminary setting of the tunnel on the
topographical Survey of India maps 3. Driving lines between the fixed
obligatory points. The correct sequence of the activities is :
A. 3,2,4,1
B. 1,2,3,4
C. 4,3,1,2
D. 2,4,3,1.
Answer => A
7. Pick up the
correct statement from the following :
A. The topographical maps of the Survey of India are useful
in the mountainous region for tunnelling.
B. The height point on the ridge is fixed with the help of
reciprocal ranging
C. The accuracy of 1 in 10,000 is required for planimetric
control
D. All the above.
Answer => D
8. Which one of the following statements is not correct in
respect of setting of an inclined tunnel :
A. Reference points are constructed at every 300 m.
B. The alignment is fixed from upper/lower apex point.
C. The level of the invert at the heading is marked by a
tape.
D. None the above.
Answer => D
9. For transferring
the'tunnel alignment through shafts, we adopt the following steps : 1. Hanging
two or more plumb lines in the shaft 2. Determining the bearing of the plumb
lines i.e. plumb plane 3. Suspending a 35 kg weight by each plumb line 4.
Immersing the weights of both the plumb lines in the buckets containingi,vater.
The correct sequence of steps is :
A. 1 2 3 4
B. 4 3 2 1
C. 1 3 2 4
D. 2 1 4 3.
Answer => D
10. For B.G. single
track, the section of the tunnel must have a width
A. 4.2 m to 4.5 m
B. 4.5 m to 4.8 m
C. 4,9 m to 5.5 m
D. 5.5 m to 5.8 m.
Answer => C
11. For B.G. single
track railway, the height of the tunnel above top of rails should be
A. 5.5 m to 5.8 m
B. 5.8 rn to 6.2 m
C. 6,7 m to 7.3 m
D. 7.3 m to 7.5 m.
Answer => C
12. The difference of heights of the tunnels above rail tops
of BG and MG tracks is kept
A. 0.30 m
B. 0.45 m
C. 0.60 m
D. 0.75 m.
Answer => C
13. For tunnels
exceeding 300 m in length, the grade should be proded below
A. 50% of the ruling gradient
B. 60% of the ruling gradient
C. 75% of the ruling gradient
D. 80% of the ruling gradient.
Answer => C
14. The advantages of providing a pair of tunnels as
compared to only one large highway tunnel is :
A. economy in cost of construction
B. avoidance of head on collisions
C. provision of separate exit and entrance of two traffic
streams
D. All the above.
Answer => D
15. Which one of the
following methods is generally adopted for tunnelling in firm ground
A. Full face method
B. Top heading and benching method
C. Drift method
D. All the above.
Answer => D
16. For full face
method, the excavation to be done is generally divided into
A. two sections
B. three sections.
C. four sections
D. five sections
Answer => B
17. Forepoling method is generally adopted for tunnelling in
:
A. soft ground
B. firm ground
C. running ground
D. None of these.
Answer => A
18. Railway tunnels, are generally
A. polycentric
B. rectangular
C. parabolic
D. circular
Answer => A
19. In case of drift method of tunnelling, the drift may be
excavated at
A. the centre
B. the bottom
C. the top
D. All of the above.
Answer => D
20. The following operations are generally employed for
tunnelling in hard rock, 1. Removing ground water, 2. Loading holes and firing
the explosive 3. Setting up and drilling 4. Grouting and lining 5. Removing
muck 6. Ventilation and removing explosion dust. The correct sequence is :
A. 3,2,6,5,1,4
B.3,4,6,1,5,2
C. 4,1,2,3,6,5
D. 5,4,2,1,3,6.
Answer => A
21. Which one of the following methods of tunnelling doe not
require the use of time bearing :
A. Linear plate method
B. Shield method
C. Compressed air method
D. All the these.
Answer => D
22. The length of the
needle beam used in needle beam method of tunnelling is usually
A. 2 m to 4 m
B. 2.5 m to 6 m
C. 4 m to 7 m
D. 5 m to 6 m.
Answer => D
23. Which one of the
following statements is not correct with regard to heading and henching method
of tunnelling.
A. Driving of tunnel is done in two portions of its section
B. Driving the top portion is done in advance of the bottom
portion.
C. After driving the top portion 3 m to 3.5 m holes are
drilled into the head and bench.
D. Firing of headholes is done just before the bench holes
are fired:
Answer => D
24. WhiCh one of the following statements is not correct for
heading and benching method of tunnelling ?
A. Drilling and mucking can be done simultaneously
B. Benching provides a plateform for working on heading
C. Removal of muck from the heading is very easy
D. None of these.
Answer => C
25. The following operations are required for tunnelling in
rockYAerrain? 1. Renmving the foul gases 2. Marking the tunnel profile 3.
Setting up and drilling 4. Checking misfire 5. Mucking The correct sequence is
:
A. 1,2,3,4,5
B. 2,3,5,4,1
C. 4,2,1,3,5
D. 2,3,1,4,5.
Answer => D
26. Pick up the correct statement regarding drilling a
tunnel from the following :
A. Holes are drilled by pneumatically operated rock drills
B. One drill is required for each 4 to 5 m2 force area
C. The diameter of the bore hole at the deepest point should
be 6 mm more than the diameter of the cartridge
D. All of the above.
Answer => D
27. The most commonly
adopted pattern of cut holes is :
A. horizontal wedge cut
B. pyramid cut
C. fan cut
D. All the above.
Answer => D
28. The cut of a tunnel face is shown in Fig. 24.2. This is
called
A. Michigan cut
B. Burn cut
C. Fan cut
D. Horizontal cut.
Answer => A
29. To attain the
required shape of the 'tunnel section, we use :
A. easers
B. trimmers
C. cut holes
D. chisels.
Answer => B
30. Pick up the explosive used for tunnelling in soft rocks
from the following :
A. blasting gelatine
B. special gelatin
C. ammonia dynamite
D. semi-gelatine.
Answer => C
31. Pick up the correct statement from the following during
tunnel excavation,
A. Oxygen should not be less than 19.5%
B. Carbondioxide should not be more than 0.5%
C. Hydrogen sulphide should not be more than 0.001%
D. All of the above.
Answer => D
32. The concentration
of the dust particles of the size 0.5 to 5 microns adjacent to the working face
should not be more than
A. 200 particles/cm3
B. 250 particles/cm3
C. 300 particles/cm3
D. 450 particles/cm3
Answer => D
33. Which one of the following linings is suitable for
shield driven tunnels particularly in the subaqueous regions :
A. Brick lining
B. stone lining
C. timber line
D. cast iron lining
Answer => D
34. Concrete lining is provided concurrently with the
driving operation in case of
A. rock terrain
B. soft rock
C. running soil
D. none of these.
Answer => A
35. High pressure
grouting is generally restored for concreting in the lining if the rock strata
is :
A. highly fissured
B. poor
C. likely to get seepage of VTater
D. All of the above.
Answer => D
36. The method of draining in the tunnels, is generally
known as
A. foredrainage
B. dewatering
C. permanent drainage
D. All of the above.
Answer => D
37. Which one of the following methods is adopted for
permanent drainage of tunnels :
A. provision of longitudinal drains
B. continuous open drains
C. concrete lining
D. All the above.
Answer => D
38. Pick up the
mechanical ventilation method used for tunnels from the following
A. blowing fresh air by ducts to the face of tunnel
B. exhausting foul air by ducts from the face of the tunnel
and permitting fresh air through the tunnel
C. blowing fresh air and exhausting foul air by ducts
D. all the above.
Answer => D
39. For hauling muck
from the tunnel, the following type of muck-car is used :
A. muck box
B. balle-ship
C. side dump car
D. All of these.
Answer => D
40. In the wooded
bulk-head, used for mucking in steep grade tunnels,
A. one opening is provided
B. two openings are provided
C. three openings are provided
D. no opening is provided.
Answer => B
41. Which one of the
following methods is generally used for the layout of the muck-car tracks
A. the grass hopper method
B. passing track method
C. the cherry picker
D. All the above.
Answer => D
42. An overhead track
on a large truss frame is required in case of car changer by
A. the grass hopper method
B. the passing track method
C. California crossing method
D. Dixon conveyor method.
Answer => A